/ home
/ program services / roads
/ Current
and Recent Projects Home
| Current Projects |
GRCC Photos
Generally, restoration activities began in the headwaters of the Mattole and
are moving down river with the exception of pilot projects. Over the past four
years the GRCC program completed the "Upriver" project covering most
of the watershed south of the Shelter Cove Road. Current projects are underway
in adjacent tributaries. The "Eubanks" project area has been underway
for two years and will reach completion this year. The "Bear Creek"
and "Blue Slide to Grindstone Creek" projects have been underway for
a year and are scheduled to reach completion in 2009 or 2010. New projects are
in the development phase in the Petrolia area, Honeydew Creek watershed, and at
select ranchlands throughout the watershed between Honeydew and Petrolia. Over
the past five years the GRCC program has worked with over 250 landowners in the
Mattole watershed and access is generally granted to 50% to 75% of the area within
each designated project. Click on "GRCC Photos" above to see before
and after images of some of our recently completed work! Eubanks Project
Area: For the past two summers GRCC projects have been improving drainages
and roads within Big Finley, Little Finley, Buck, Deerlick, Eubanks, Nooning Creek
tributaries to the Mattole River. After the project reaches completion in the
summer of 2008, approximately 57,970 cubic yards of sediment will have been prevented
from entering the Mattole River watershed over the three years of implementation
work. Several miles of road have been reshaped by crowning and outsloping road
segments. Nearly fifty culverts have been installed, all designed to withstand
a 100-year flood events. In addition, some of the most exciting and large scale
GRCC projects were performed replacing old culverts that were impeding fish access
and installing bridges or bottomless pipe arches. These structures allow salmon
and steelhead trout to freely migrate under the road expanding their spawning
and rearing habitat. Bear Creek Project Area: The GRCC program
is working to reduce sediment in the Bear, French and Wolf Creek sub-watersheds
to the Mattole River. Over the next two summer work seasons, 35,900 cubic yards
of sediment will be prevented from entering the streams, approximately 3,590 dump
truck loads of dirt. Twenty-five culverts will be replaced, numerous drivable
rock-armored fords will be installed on seasonal roads and miles of road will
be reshaped to reduce surface erosion. Local operators complete all of the heavy
equipment work.
Blueslide, Mattole Canyon and Grindstone Creek Project
Areas: The GRCC Program plans to stabilize 108,960 cubic yards of sediment
over the next few work seasons. This area of the Mattole has unstable geology
and is prone to having large landslides. Numerous instream sites are scheduled
to stabilize the toe of these slides with rock wing deflectors and willow bioengineering
structures. These structures are designed to stabilize the toe of these slides
by keeping the force of the water away from the unstable bank, keeping the water
flowing in the center of the channel and allowing for regeneration of the riparian
vegetation that naturally stabilizes the streambank. Several miles of road will
also be storm-proofed within this project area. Petrolia Project Area:
In 2007, GRCC personnel performed a sediment source assessment on the roads and
erosive streambanks within the lower Mattole area. This project area encompasses
the area from McGuiness Creek down to the Mattole River estuary. GRCC staff identified
over 100 sites with the potential to reduce 72,540 cubic yards of sediment from
entering the watercourses. Currently funding to treat these sites is approximately
25% secured and the implementation phase will probably begin summer 2008 and reach
completion in 2011. Ranchlands Water Quality Program: Due to the
fact that the majority of land between Honeydew and Petrolia is in ranchland ownership,
the MRC has developed this program with the goal of outreach and relationship
building with this important set of landowners. So far sediment assessments have
been performed on four ranches (not including three large ranches within the Bear
Creek and Blueslide to Grindstone project areas that have participated in the
GRCC program). GRCC staff is actively pursuing further ranchland involvement a
development of implementation projects on these properties. Summary and
Conclusion: The GRCC program has expanded and become well funded over the
past few years. In 2007, expenditures were near $1,500,000 and a similar volume
of work is expected over the next few years. New landowner involvement is always
welcomed as the GRCC program works to further its goal of sediment reduction and
improved aquatic habitat throughout the watershed. Although the program follows
a general action plan moving from one project area to another, exceptions can
be made to include pilot projects if they have the potential to significantly
reduce erosion. Please don't hesitate to contact GRCC staff with any questions
or concerns you might have regarding erosion and sediment delivery on your property!
|